G-Force prepares draft plan of subdivision and draft plan of condominium applications and manages their conditions to registration. A plan of subdivision is a surveyed plan, approved under section 51 of the Planning Act, that creates new lots, blocks and streets. A draft plan of condominium follows a similar approval process and sets up condominium ownership.

When a project needs a draft plan

  • Land is to be divided into several lots, particularly with a new street.
  • Townhomes, offices or commercial units are to be owned as condominiums.

What G-Force does on a draft plan

  • Reviews the lotting and layout with the surveyor and the engineers.
  • Writes the Planning Justification Report.
  • Prepares the draft plan application and responds to comments.
  • Tracks the draft approval conditions through to clearance and registration.

What the Planning Act sets

  • Approval comes in two stages: draft approval with conditions, then final approval and registration once the conditions are met.
  • Every draft approval of a plan of subdivision must carry a lapsing period of at least three years, unless a regulation prescribes a different period.
  • An applicant may appeal to the Ontario Land Tribunal if no decision is made within 120 days of a complete application.
  • In Peel, Halton and York Regions, the local city or town has been the approval authority for plans of subdivision since July 1, 2024.

These points are explained in full in the guide Plans of Subdivision in Ontario: Process and Appeals.

Other planning services

This page is general information about Ontario’s planning system, not legal or planning advice. Requirements and timelines change and vary by municipality — confirm the current rules for your site with our team.