Planning applications in Ontario that are approved on schedule usually share five habits: the approval route is settled before design starts, the municipality is consulted early, the first submission is complete and internally consistent, neighbours and the ward councillor hear about the project before the public meeting, and comments and conditions are run as a schedule. Applications that stall have usually skipped one of them.
Key points
- Pre-consultation is no longer mandatory in Ontario. Since Bill 185 (2024), the Planning Act requires municipalities to permit applicants to consult before applying, and municipalities can no longer pass a by-law requiring it.
- An Ontario municipality can require studies beyond the provincially prescribed information only if its official plan provides for them, and it must tell the applicant within 30 days after the fee is paid whether the application is complete.
- The Planning Act lets an applicant appeal to the Ontario Land Tribunal if no decision is made within 120 days on an official plan amendment, 90 days on a zoning by-law amendment (120 days if filed on the same day as a related official plan amendment), 60 days on a site plan, or 120 days on a plan of subdivision.
- The application-fee refunds that Bill 109 (2022) imposed on municipalities for late zoning and site plan decisions were repealed by Bill 185 in 2024.
- Under subsection 34 (1.4) of the Planning Act and Ontario Regulation 545/06, a minimum setback in a zoning by-law is deemed to be 90 per cent of the stated distance on parcels of urban residential land outside the Greenbelt Area, except in certain prescribed areas.
Habit 1: Which planning approval does the project need?
Successful planning applications in Ontario settle the approval route before the design is drawn. The main routes under the Planning Act are:
- Official plan amendment — a change to the municipality’s long-range land-use policy document.
- Zoning by-law amendment (rezoning) — a change to the by-law that sets permitted uses, height, density and setbacks for a property.
- Minor variance — a small exception to a zoning standard, decided by the municipality’s Committee of Adjustment.
- Consent (severance) — approval to divide land without a plan of subdivision.
- Plan of subdivision — approval to divide land into multiple lots and blocks.
- Site plan approval — approval of plans showing where buildings, facilities and works will sit on the site.
Under subsection 45 (1) of the Planning Act, a minor variance must meet four tests: it is minor, it is desirable for the appropriate development or use of the land, and it maintains the general intent and purpose of both the zoning by-law and the official plan. A request that cannot meet those tests belongs in a rezoning; see minor variance or rezoning.
Since 2025, subsection 34 (1.4) deems a minimum setback — the required distance between a building and a lot line — to be 90 per cent of the by-law figure on parcels of urban residential land outside the Greenbelt Area, except in certain prescribed areas. Where that rule applies, a small setback shortfall may not need a variance at all; confirm with the municipality’s zoning staff before relying on it.
Habit 2: Is pre-consultation still mandatory in Ontario?
Pre-consultation is a meeting with municipal staff before a planning application is filed, and in Ontario it is now the applicant’s choice. Bill 185 (2024) rewrote subsections 22 (3.1), 34 (10.0.1), 41 (3.1) and 51 (16.1) of the Planning Act: the municipality “shall permit” applicants to consult before applying, and the earlier power to require consultation by by-law was removed.
Optional is not the same as unimportant. Use the meeting to confirm three things in writing: which approvals staff think the project needs, which studies the official plan requires, and which departments and outside agencies will review the file.
Habit 3: What makes a planning application complete in Ontario?
A complete planning application in Ontario contains the information prescribed by provincial regulation, any other material the municipality is entitled to require, and the fee. Under subsection 34 (10.2) of the Planning Act for rezonings, with parallel provisions for other application types, a municipality may require additional studies only if its official plan contains provisions about those requirements.
- 30-day answer. Under subsection 34 (10.4), the municipality must notify the applicant within 30 days after the fee is paid whether the application is complete.
- The clock waits. Under subsection 34 (10.3), until the required material and fee are received the municipality may refuse to accept the application, and the statutory decision period does not begin.
- Disputes go to the Tribunal. Under subsection 34 (10.5), either side may ask the Ontario Land Tribunal — the provincial body that hears planning appeals — to decide whether the material has been provided or whether a study requirement is reasonable.
- Study lists are harder to expand. Under subsection 17 (21.1), added by Bill 17 in 2025, a municipality needs the Minister’s written approval before amending its official plan to add or change study requirements.
Complete is the legal minimum. The practical standard is consistency: unit count, floor area, height, parking and setbacks should be identical on the drawings, in the planning report (the planner’s written case that the proposal meets policy), in the technical studies and on the application form.
Habit 4: When should you talk to neighbours and the councillor?
Neighbours and the ward councillor should hear about a planning application from the applicant before they read about it in a formal notice. Under subsection 34 (12) of the Planning Act, council must hold at least one public meeting before passing a zoning by-law amendment, and under subsection 45 (6) the Committee of Adjustment must hear every person who wishes to speak for or against a minor variance. A fence, a moved driveway or a changed window is cheaper to settle before that meeting than at it.
Appeal rights are narrower than many people assume. Under the Planning Act, appeals of rezonings, official plan amendments, minor variances and consents are generally limited to the applicant, the Minister, public bodies and listed “specified persons” such as utilities and railways, so a neighbour who simply objects no longer has a right of appeal; the Ontario Land Tribunal guide covers the detail. Council and the committee still decide, which is reason enough to engage.
Habit 5: How long does a municipality have to decide a planning application?
The Planning Act sets decision periods for Ontario municipalities, after which the applicant may appeal the lack of a decision to the Ontario Land Tribunal:
- Official plan amendment: 120 days (subsection 22 (7.0.2)).
- Zoning by-law amendment: 90 days, or 120 days when filed on the same day as a related official plan amendment (subsections 34 (11) and (11.0.0.0.1)).
- Site plan: 60 days (subsection 41 (12)).
- Plan of subdivision: 120 days (subsection 51 (34)).
These periods are appeal triggers, not delivery promises. Bill 109 (2022) made municipalities refund application fees when they missed the zoning and site plan periods; Bill 185 repealed those refund rules in 2024.
The applicant has a schedule to keep as well. Keep one comment matrix — a table of every reviewer comment, who answers it and by when — resubmit everything together, and track conditions of approval the same way. Under subsection 53 (41), a consent application is deemed refused if its conditions are not fulfilled within two years after notice of the decision.
What to do when a planning application has stalled
A stalled planning application in Ontario usually has one of three causes.
- Not accepted as complete. Ask staff to name the missing item and the official plan provision that requires it. If the disagreement is real, the Planning Act allows a motion to the Ontario Land Tribunal to settle it.
- Circling in comments. Request one meeting with every commenting department, table a single consolidated response, and agree what the next submission must contain.
- Past the statutory period with no decision. An appeal for non-decision is available, but it hands the decision to the Tribunal. Weigh it against a firm council or committee date before filing.
The G-Force view
We treat a planning application as a project with a critical path, not a form to be filed: the route is chosen before the drawings, the package is checked against itself before staff see it, and every comment and condition has an owner and a date. None of that guarantees an approval; it removes the avoidable reasons for delay.
Common questions
Is pre-consultation mandatory for a planning application in Ontario?
No. Since Bill 185 (2024), the Planning Act requires municipalities to permit applicants to consult before applying, and municipalities can no longer pass a by-law requiring it. Pre-consultation is still worth doing, because it is where the required studies and reviewing agencies are identified.
What is a complete planning application in Ontario?
A complete application contains the information prescribed by provincial regulation, any other material the municipality's official plan allows it to require, and the fee. The municipality must tell the applicant within 30 days after the fee is paid whether the application is complete, and the statutory decision period does not begin until it is.
How long does an Ontario municipality have to decide a planning application?
The Planning Act allows an appeal to the Ontario Land Tribunal if no decision is made within 120 days on an official plan amendment, 90 days on a zoning by-law amendment (120 days if made on the same day as a related official plan amendment request), 60 days on a site plan, or 120 days on a plan of subdivision.
Do Ontario municipalities still refund application fees when they miss a planning deadline?
No. Bill 109 (2022) required municipalities to refund fees when zoning and site plan decisions were late, but Bill 185 repealed those refund rules in 2024. The statutory decision periods remain as triggers for an appeal to the Ontario Land Tribunal.
Do I still need a minor variance for a small setback shortfall in Ontario?
Possibly not. Under subsection 34 (1.4) of the Planning Act and Ontario Regulation 545/06, a minimum setback is deemed to be 90 per cent of the by-law distance on parcels of urban residential land outside the Greenbelt Area, except in certain prescribed areas. A larger shortfall still needs a minor variance that meets the four tests in subsection 45 (1). Confirm with the municipality's zoning staff before relying on the rule.
About G-Force
G-Force Urban Planners & Consultants is a land-use planning firm in Mississauga, Ontario, led by Manni Chauhan, a Registered Professional Planner with more than 30 years in planning and development. The firm takes development proposals through municipal approvals across Ontario. Meet the team or tell us about your site.