An Official Plan Amendment (OPA) changes a municipality’s official plan so that a project the plan does not currently allow can be considered. In Ontario an OPA is needed when a proposal conflicts with the plan itself, not just with the zoning beneath it. The plan has to be amended before anything else can proceed, which makes the OPA the most policy-heavy instrument in Ontario’s approvals toolkit.
Key points
- An official plan is the council-adopted document that sets a municipality’s goals, objectives and policies for land use. Under section 24(1) of the Planning Act, zoning by-laws must conform with it.
- Under section 22 of the Planning Act, any person or public body can ask a council to amend its official plan. If council refuses, or does not adopt the amendment within 120 days of receiving a complete request, the applicant can appeal to the Ontario Land Tribunal.
- Pre-consultation before an Official Plan Amendment application has been voluntary for the applicant since June 6, 2024. Municipalities must permit it but can no longer require it.
- The Regions of Durham, Halton, Niagara, Peel, Waterloo and York are now “upper-tier municipalities without planning responsibilities” under the Planning Act and no longer approve official plan amendments adopted by their local municipalities.
- An adopted Official Plan Amendment can be appealed within 20 days after notice is given, and only by the applicant, the Minister, the approval authority, a public body, a “specified person”, or a registered owner of land the amendment would apply to.
- Every decision on an Official Plan Amendment must be consistent with the Provincial Planning Statement, 2024, which replaced the Provincial Policy Statement, 2020 and the Growth Plan for the Greater Golden Horseshoe on October 20, 2024.
What is an official plan, and what does an amendment change?
An official plan sets out a municipality’s long-term vision for land use — the blueprint above the zoning. It says where housing, employment and services will go, and typically assigns each area a land use designation with policies on what can be built there. Zoning by-laws put those policies into effect, and no by-law may be passed that does not conform with the plan.
An Official Plan Amendment is a formal change to that document. Council can start one itself; this guide is about the amendment a landowner requests for a particular site.
When is an Official Plan Amendment required?
- Changing a land-use designation — industrial to residential, agricultural to development lands.
- Exceeding designated limits — a 10-storey proposal where the plan caps the area at six.
- Site-specific policy — a special policy to allow a unique project the plan didn’t anticipate.
An OPA usually runs in parallel with a rezoning. Section 24(2) of the Planning Act lets council pass the zoning by-law before the amendment is in effect; the by-law has no force unless the amendment comes into effect.
Two kinds of request carry a limit worth knowing before filing:
- Employment land. Where the official plan has policies on removing land from an area of employment, a refusal of a request to remove land, or a failure to decide it, cannot be appealed (section 22(7.3)).
- Settlement boundaries. A refusal generally cannot be appealed if the request would create a new settlement area or expand one into the Greenbelt Area.
One older limit is gone. The two-year ban on requesting amendments to a new official plan or secondary plan was repealed on November 28, 2022.
How does the Official Plan Amendment process work?
The steps for a requested Official Plan Amendment resemble a rezoning and are set by sections 17 and 22 of the Planning Act:
- Consultation. Under section 22(3.1), council must permit an applicant to consult before applying. Since June 6, 2024 it cannot make that mandatory.
- Complete request. The request must include the information prescribed in Ontario Regulation 543/06, plus any studies the official plan itself requires. Council has 30 days after the fee is paid to say whether the request is complete.
- Public meeting. Council must hold at least one public meeting, no earlier than 20 days after notice, unless the official plan sets out alternative consultation measures. No meeting is required if council refuses the request.
- Council decision. Council adopts the amendment by by-law or refuses it, and gives written notice within 15 days.
- Approval and appeal. The amendment then goes to an approval authority or straight into a 20-day appeal period.
Who gives final approval to an Official Plan Amendment?
Final approval of an Official Plan Amendment in Ontario depends on where the land is. There are three routes:
- Exempt from approval. Ontario Regulation 525/97 exempts all amendments to the official plans of the municipalities it lists from the Minister’s approval. The list includes Mississauga, Brampton, Caledon, Oakville, Milton, Vaughan and Markham. Council’s adoption is the last municipal step, and the amendment takes effect the day after the appeal period ends if no one appeals. The Minister can remove the exemption for a particular amendment.
- Upper-tier approval. Where a county or region still has planning responsibilities, it is the approval authority for its local municipalities’ amendments under section 17(2). It can approve, modify or refuse, and a failure to give notice of a decision within 120 days can be appealed.
- Minister’s approval. In every other case, the Minister of Municipal Affairs and Housing is the approval authority.
Until recently the upper-tier route applied in the regions around Toronto. It no longer does. Halton, Peel and York lost their planning responsibilities on July 1, 2024, Durham and Waterloo on January 1, 2025, and Niagara on March 31, 2025. Under section 70.13 of the Planning Act, the parts of the regional official plan that applied in each local municipality are deemed to be an official plan of that municipality until it revokes or amends them. A site in one of these regions may have to be tested against two documents.
Who can appeal an Official Plan Amendment decision?
- Refusal or no decision. Under section 22(7), the person who requested the amendment, the Minister and the approval authority can appeal a refusal, or a failure to adopt within 120 days. A refusal must be appealed within 20 days after notice of it is given.
- Adoption or approval. Under sections 17(24) and 17(36), the appeal period is 20 days after notice is given. Only the applicant, the Minister, the approval authority (where the amendment is exempt), a public body, a specified person, or a registered owner of land to which the amendment would apply can appeal. Public bodies, specified persons and owners must have made submissions to council before adoption. A “specified person” is a defined list of utilities, pipeline and railway companies, airports and certain nearby industrial and aggregate operators.
Before June 6, 2024, any person who had made submissions could appeal. The Cutting Red Tape to Build More Homes Act, 2024 (Bill 185) ended that for neighbours and residents’ groups. See our guide to Ontario Land Tribunal appeals.
What makes an Official Plan Amendment succeed?
An Official Plan Amendment asks a municipality to change its own long-term policy, so the evidence bar is higher than for a rezoning. A Planning Justification Report is where the case is made in writing.
- Keep it surgical. A narrow, site-specific amendment is far more palatable than a sweeping policy rewrite. Tailor the change to your land.
- Prove the public interest. Market evidence, vacancy data, growth numbers — show the designation no longer serves the community as well as the proposal does.
- Respect the hierarchy. Under section 3(5) of the Planning Act the decision must be consistent with the Provincial Planning Statement, 2024 and conform with any provincial plan that applies, such as the Greenbelt Plan. An amendment that collides with them will not survive.
- Engage politically as well as technically. OPAs are sensitive precisely because they set precedent. Councillors and communities that understand the why are far less likely to fight the what.
The G-Force view
An OPA is where planning stops being about rules and becomes about vision — and vision has to be argued, not asserted. Our OPA files pair the policy case with the human one: what the community gains, and why this site, now. That is the argument councils can carry.
Common questions
What is an Official Plan Amendment in Ontario?
An Official Plan Amendment (OPA) is a formal change to a municipality's official plan, the council-adopted document that sets its land use policies. A landowner requests one under section 22 of the Planning Act when a proposal conflicts with the plan itself and not just the zoning.
Who approves an Official Plan Amendment in Mississauga or Brampton?
Council. Ontario Regulation 525/97 exempts amendments to the official plans of Mississauga, Brampton and the other municipalities it lists from the Minister's approval, and Peel Region has had no approval role since July 1, 2024. An adopted amendment takes effect the day after the 20-day appeal period if no one appeals.
How long does council have to decide an Official Plan Amendment request?
Under section 22(7) of the Planning Act, the applicant can appeal to the Ontario Land Tribunal if council refuses the request or does not adopt the amendment within 120 days of receiving a complete request.
Can neighbours appeal an Official Plan Amendment in Ontario?
Not generally. Since June 6, 2024, an adopted amendment can be appealed only by the applicant, the Minister, the approval authority, a public body, a specified person, or a registered owner of land the amendment would apply to.
Do regional governments still approve local official plan amendments?
Not in Durham, Halton, Niagara, Peel, Waterloo or York. Those regions are now upper-tier municipalities without planning responsibilities under the Planning Act. Counties and regions that still have planning responsibilities remain approval authorities for their local municipalities.
Can I apply to amend a brand new official plan?
Yes. The Planning Act's two-year ban on requests to amend a new official plan or secondary plan was repealed on November 28, 2022. Requests to change certain protected major transit station area policies still need council's permission.
About G-Force
G-Force Urban Planners & Consultants is a land-use planning firm in Mississauga, Ontario, led by Manni Chauhan, a Registered Professional Planner with more than 30 years in planning and development. The firm takes development proposals through municipal approvals across Ontario. Meet the team or tell us about your site.